Nursery foundation

Client: Southern Rainforest

Suburb: Launching Place

Project: Nursery fill pad, stone retaining wall, screw piles and concrete slab

Duration: 14 weeks

Scope: Raise building envelope above 1 in 100 year flood level, retain fill pad with stone walls, then use steel and concrete to provide solid foundation

Process:

IMG_5780IMG_5829IMG_6458IMG_5938IMG_6031IMG_6079IMG_6099IMG_6410IMG_6458IMG_6502IMG_6513IMG_6522IMG_6810IMG_6921IMG_6928IMG_7192IMG_7287IMG_7297IMG_7448IMG_7464IMG_7495IMG_7502IMG_1852IMG_1856IMG_1879IMG_1890

 

 

Bluestone capped dry-stone retaining wall

Client: Damian.

Suburb: Don Valley.

Project: Stone retaining wall.

Duration: 3 weeks.

Scope: Dry stone retaining wall with bluestone capping and base of wood fired oven.

Process:

IMG_6490

IMG_6497IMG_7212IMG_7322IMG_7266IMG_7372IMG_7384IMG_7394IMG_7399IMG_7401IMG_7402IMG_7403IMG_7432IMG_7433

Low maintenance luxury

Client: Winifred

‘I am pleased to say that I have been extremely satisfied with the work carried out by Brett Cowan and Southern Rainforest. The landscape, design & construction work is of excellent standard & I have no hesitation recommending Brett for this type of work.’

Suburb: Glen Iris

Project: Back Garden

Duration: 8 weeks

Scope: Transform labour intensive yard into low maintenance and enjoyable garden

Process:

Backyard was a mix of different materials and was constant upkeep, as well as not being very useable. Bluestones were reused as an edge, whilst other materials were recycled.

IMG_1237

IMG_1238 IMG_1239 IMG_1240 IMG_1244

 

Footings were installed and blockwork constructed. Due to narrow access, all material had to be wheeled in by hand.

IMG_2971 IMG_2977 IMG_2998 IMG_3004

 

After compaction, reinforced concrete slab was installed and paving laid, grouted and sealed. Other additions were, synthetic turf, clothesline, sideway stepping stones, bluestone path, steps, edge and mulching.

IMG_1704IMG_1695IMG_1681IMG_1674IMG_1672IMG_1667IMG_1663IMG_1641IMG_1629

IMG_1617IMG_1610IMG_1619IMG_1634

Clinker wall and driveway

 

Clients: Anh & Danh

Suburb: Glen Iris

Project: Front garden

Duration: 8 weeks

Scope: Front brick retaining wall needed replacing and driveway needed widening to suit clients growing family.

Process:

After 50 years of weathering, retaining wall and driveway needed replacing.

20121009_123752

20120830_173139

20120830_173420As the clinker bricks are no longer in production they were cleaned and reused, this added character and matched house. Other additions were, paved driveway on concrete base, lighting, irrigation, instant turf, mulching and planting.

IMG_0988

IMG_0962

IMG_0961

IMG_1024IMG_1015IMG_1014IMG_0973IMG_0956

IMG_0957

Balwyn Backyard

Clients: Sally & Rob

Suburb: Balwyn

Project: Backyard

Duration: 5 – 6 weeks

Scope: Clients had tried previously to landscape garden, though were extremely time poor and as such could not complete project. Being engineers they designed lay out and positioning of wall. Was quite complex due to clients not wanting drains or grates and so all paved area had to fall away from house and at the same time not pool along wall.

Process: On east side of house  paving commenced with a small courtyard

 

Then work commenced on westside of house, pool and paving was to remain, though everything else was to go.

Then clean up began and the construction of the great wall began.

 

Once complete concrete base was installed.

 

Then paving of 800 x 400 sandstone was laid.

Balwyn front garden

 

Clients: Sally & Rob

Suburb: Balwyn

Project: Front garden

Duration: 4 – 5 weeks

Scope: Client’s had a very busy lifestyle and over 20 years had no time for their front garden. They requested a low maintenance garden and new driveway.

 

Process:

First glance, 20 years of growth

 

After vegetation was removed, shaping and excavation began.

 

Concrete base was then installed.

 

Then a 3 blend mix of clay pavers were selected. At the time it seemed too much, though as the photos display the 3 blend  creates a striking appearance.

 

Paving complete, now time for planting.

Project complete and clients happy.